Mortenson Builds Its Own Tools, Vendors Eye Token Pricing, and Groundworks Is Coming: Where Should Innovation Money Go?


Mortenson's Gene Hodge on why the company spends its innovation budget on its own R&D facility and what seven years of duct bank work taught it. Plus: Alain Waha on software priced by the token.

THE EXECUTIVE BRIEFING
THIS WEEK’S KEY TAKEAWAYS

Key Takeaway 1:

Mortenson spends most of its innovation budget building its own tools, including a 90,000-square-foot R&D facility. Gene Hodge says an industrialized data center needs half the on-site labor hours of a conventional one.

Key Takeaway 2:

Alain Waha, Buro Happold's CTO, expects software vendors to move from seat licenses to charging for AI compute in tokens. He sees most tokens spent in design firms going to reading submittals and RFIs today.

Key Takeaway 3:

We are launching Groundworks, a construction robotics adoption summit, in London on November 11, 2026. Speakers come from UK government, Tier 1 contractors and robotics firms, with live demos on the day.

❝

"This idea that 100% of every single project is a snowflake and it will only exist one time is madness."

Gene Hodge, Mortenson

7 THINGS WORTH YOUR ATTENTION
ON THE RADAR THIS WEEK

  • Data Centre Design Summit, London, 6-7 October - AI Growth Zones, liquid cooling and modular build. (More)

  • RICS UK&I QS & Construction Conference, online, 6-7 October - economic outlook, insolvency risk, Tideway lessons. (More)

  • Asphaltica opens in Bologna 7 October - road paving and infrastructure, alongside SAIE until 10 October. (More)

  • AGC of California's CONSTRUCT conference, Indian Wells, 6-9 October - contractors gather in person. (More)

  • Bisnow data center construction conference, Dallas, 6 October - power, land and delivery in focus. (More)

  • Mass Timber+, Philadelphia, 6-8 October - mass timber, light frame and offsite wood construction. (More)

  • SAIE opens in Bologna 7 October - building materials, digital tools and prefabricated structures, through 10 October. (More)

POWERED BY:

The multiplayer planning platform where construction teams plan together, stay aligned, and deliver projects faster.

The construction intelligence platform delivering data and insights to act faster and outperform, from site to boardroom.

The #1 construction management software for growing companies. Manage your projects from Tender to Handover.

FULL EXECUTIVE BRIEFING
Mortenson Builds Its Own Tools, Vendors Eye Token Pricing, and Groundworks Is Coming: Where Should Innovation Money Go?


In 2003, Gene Hodge was an intern at one of the largest builders in America. He was handed a spreadsheet of 18,000 punch list items on live projects and told to close every one before the internship ended. Each morning he printed pages, walked the site, ticked items off with a pen, and then ticked them off again on the computer.

Gene is now Vice President of I4 and Innovation at Mortenson, which ranked tenth on ENR's Top 400 this year with $10.8 billion in 2025 revenue.

❝

"You now have an iPad, but your process is a little more efficient, it's not radically changed."

Gene Hodge on what has changed on site since 2003.

Why Mortenson Builds Its Own Tools

I asked Gene what Mortenson is shopping for, and he said, "I don't know if there's anything I'm shopping for." Most of the innovation budget goes into building capability in house. A few years ago an internal leadership group told the business it was treating innovation as a hobby. A project site has a margin, a date, and a safety record to protect, so little gets tried there. The R&D facility is where things are expected to cost money and fail the first time.

Area

Where it started

Where it is now

R&D facility

40,000 square feet, opened last year

90,000 square feet, about 40 people

Precast duct bank

Not faster and cost more

Cost par and significantly faster, after about seven years

Data center on-site labor

Non-industrialized build

Cost par and significantly faster, after about seven years

Solar indicative budget

About four days of estimator time

First draft in about an hour

The duct bank figures come from seven years of learning in a factory setting, and Gene says Mortenson has probably had more failures than successes along the way. Mortenson also signed a Goldbeck joint venture in August to bring factory-built construction to US data centers from 2027.

Gene sees little AI impact on Mortenson's job sites so far, with the gains coming before construction. The solar estimating model was built after the company pulled its actual cost data together, and Gene frames the choice as starting from 80% of the work in place or starting from zero. Headcount stays put. Mortenson has more work than people, so efficiency means taking on more of it.

Gene links the slow pace of change to the fragmented structure of the industry. He also described what happens to the contractor if projects start running clean.

❝

“That's a lot of what construction contractors do. It's kind of manage the chaos of a project."

Gene Hodge, on what AI does to the contractor's role

Mortenson's answer is vertical integration across self-performed work, offsite manufacturing, and its own design and engineering. Gene set manufacturing up separately because "In construction we reward heroics," while in manufacturing "it needs to be boring."

Watch: Why a $10.8B Builder Stopped Treating Innovation Like a Hobby

Alain Waha on Paying Software by the Token

Alain Waha, Chief Technology Officer at Buro Happold, joins our live show once a month and was at Autodesk University with me. Our Autodesk University coverage ran two weeks ago. Alain's own takeaway from the week was that Autodesk will aim to charge customers more for its technology, a hope for its shareholders and for the industry that still has to be proven.

❝

"When we talk about artificial intelligence, what we're really talking about is companies selling inference compute."

Alain Waha, Buro Happold

Software is priced by the seat today. Alain expects a move toward charging for compute, meaning tokens, which measure how much thinking the machine does for the customer. In his Revit example, a normal day of seat use might cost eight tokens, while asking an AI assistant to add a floor, work that would take a person a day, would cost 80. The vendor's pitch becomes selling assistance and "thinking multiplication" at a higher price, with the customer seeing the benefit.

Alain sees tokens being spent in two places today:

  • Reading documents. Customers send 20,000 pages, and the 10 that matter are buried inside. He rates submittals and RFIs as very strong use cases.

  • Generating design. He does not yet see heavy token consumption from people generating design.

His last point was that "what we are seeing from vendors is just the new technology on the old process," and the old process of drawings and documents was designed for human brains. Alain wants AI to multiply those brains by scanning every requirement on a job, finding where they conflict, and flagging where they are tighter than they need to be so the client can be asked to relax them.

Groundworks

Two years ago I searched Spotify for "construction robotics" before a run and found two podcasts, one of them ours. We started publishing on the subject, and it did not go well, since few people were interested at the time.

We are now launching Groundworks, a construction robotics adoption summit. Confirmed speakers so far come from the UK government, Tier 1 contractors, robotics firms in the UK and Europe, and strategic players, with live robot demos on the day. The aim is to get more of these machines doing real work on real jobs.

November 11, 2026 | London | groundworkssummit.com

Five Quick Hits

Diesel. It hit about £2 a litre on September 28, a record and 42% above January's roughly £1.41. Construction Enquirer puts the added cost for UK infrastructure at around £590 million a year, and the Construction Plant-hire Association wants the 5p duty cut extended past December.

Grid connections. The UK government launched Great British Grid on September 29, a publicly owned investor inside Great British Energy, with plans to widen self-build rights for connections. Ireland's similar reforms cut connection times by up to 11 months, and long-term funding waits for a future Spending Review.

Accenture. It launched Accenture Construct, a business of more than 5,000 practitioners that combines Accenture's existing capital projects business with 11 acquisitions, including Soben in the UK.

Data center financing. Goldman Sachs estimated earlier this year that about 60% of US data center capacity scheduled for the following 12 months would arrive on time, against 72% historically. Steve Eisman, the investor from The Big Short, says the Enron-era practice of parking debt in a special purpose vehicle is back, and he points to Meta's Louisiana campus, where the vehicle carries about $27 billion of debt and Meta holds 20%.

AMD and World Labs. AMD agreed on September 28 to buy Fei-Fei Li's company for $8.2 billion in stock, and Fei-Fei becomes AMD's chief scientist at closing. World Labs was valued at about $5 billion after a February round that included $200 million from Autodesk, an investment Alain raised when we covered world models in March.

Gene's view on measuring all of this is that "anyone asking what's the ROI on innovation is not interested in innovating, most likely." We would like to hear from CFOs on whether that holds up when the company behind it is family-owned with $10.8 billion in revenue.